LNG Terminal Overview
The Project includes setting up of a 5 MMTPA LNG Port for LNG regasification using a FSRU along with a FSU at Jafrabad in Amreli district of Gujarat. The Project capacity can be further ramped up to 10 MMTPA in future. The Project is being developed under a concession from Gujarat Maritime Board (GMB). The Project has already received the Environmental Clearance & CRZ approval from the Ministry of Environment and Forests, Govt. of India.
Key Project Components
The key Project components are as under:- Project Land: The Project will be implemented over a 97 Hectares (Ha) land parcel.
- Capital Dredging & Land Reclamation: The harbour area will be dredged to achieve a minimum depth of 14.5 meter. The total dredging volume is estimated to be 8.52 million m3. Dredging contract will also include reclamation of land.
- Breakwater & Shore Protection: Breakwater is required for providing tranquil conditions for berthing and LNG unloading throughout the year. The Breakwater construction includes transportation and installation of rock works, fabrication, transportation and installation of concrete armour made up of Accropode-II, transportation and setting up of M-40 grade concrete for the wave wall
- Jetty & Platform:LNG Jetty will be constructed as part of the Project, capable of handling FSRU on one side and LNGC on the other side
- Onshore Works, Utilities & Facilities: The Onshore facilities include development of green belt, construction of buildings and pipeline corridor till delivery point, installation of metering units, electric system, fencing, fire water storage tanks, amenities etc. Additionally, Utilities includes marine equipment like moorings, fenders, lines, berthing aid systems, etc.